Word Problems

Work, Rate & Pipes

Solve problems involving pipes filling tanks, people completing jobs, and combined work rates

Explanation & Worked Examples

The Core Idea: Rate = 1 ÷ Time

Every worker or pipe has a rate — the fraction of the job it completes per unit of time.

Rate = 1 ÷ Time to complete the whole job

For example:

  • Pipe A fills a tank in 4 hours → Rate = 1/4 of the tank per hour
  • Person B completes a job in 10 days → Rate = 1/10 of the job per day

Why Rates Add

When two or more workers/pipes operate at the same time, their rates add together because each is contributing independently:

Combined Rate = Rate₁ + Rate₂ + Rate₃ …

A drain pipe subtracts from the combined rate instead of adding.

Think of it this way: If Pipe A fills 1/4 of the tank every hour and Pipe B fills 1/6 every hour, after one hour together they have filled 1/4 + 1/6 = 5/12 of the tank. The whole job takes 12/5 hours.

The Formula

To find the time taken when multiple sources work together:

Step 1 — Find each rate
Rate = 1 ÷ (individual time)
Step 2 — Add (or subtract) rates
Combined Rate = R₁ + R₂ − R_drain
Step 3 — Find combined time
Time = 1 ÷ Combined Rate

Shortcut for Two Sources

When exactly two pipes/workers are involved, there is a direct formula:

T = (A × B) ÷ (A + B)

where A and B are the individual times. This only works for two filling sources — do not use it when there is also a drain.

Common mistake: Do not average the two times. If Pipe A takes 4 h and Pipe B takes 6 h, the answer is NOT (4 + 6) / 2 = 5 h. It is (4 × 6) / (4 + 6) = 24/10 = 2.4 h — faster than either pipe alone.

Easy Examples

Direct application of the combined rate formula.

Example 1 — Two Pipes

Pipe A fills a tank in 4 hours. Pipe B fills it in 6 hours. Both are opened together. How long to fill the tank?

1Rate of A = 1/4  |  Rate of B = 1/6
2Combined rate = 1/4 + 1/6 = 3/12 + 2/12 = 5/12 per hour
3Time = 1 ÷ (5/12) = 12/5 = 2 hours 24 minutes
Example 2 — Two Workers

Person A can paint a fence in 8 days. Person B can paint it in 12 days. Working together, how long does it take?

1Rate of A = 1/8  |  Rate of B = 1/12
2Combined = 1/8 + 1/12 = 3/24 + 2/24 = 5/24 per day
3Time = 24/5 = 4 days and 19.2 hours ≈ 4.8 days
Example 3 — Using the Shortcut

Tap A fills a bath in 10 minutes, Tap B in 15 minutes. Both on together — how long?

1T = (A × B) ÷ (A + B) = (10 × 15) ÷ (10 + 15)
2T = 150 ÷ 25 = 6 minutes

Medium Examples

These involve a drain pipe, a delayed start, or finding one unknown time.

Example 1 — Fill Pipe + Drain Pipe

Pipe A fills a tank in 4 hours. Pipe B (a drain) empties it in 12 hours. Both are open. How long to fill the tank?

1Fill rate (A) = +1/4  |  Drain rate (B) = −1/12
2Net rate = 1/4 − 1/12 = 3/12 − 1/12 = 2/12 = 1/6 per hour
3Time = 1 ÷ (1/6) = 6 hours
Example 2 — Find One Unknown Time

A and B together finish a job in 6 days. A alone takes 10 days. How long does B alone take?

1Combined rate = 1/6  |  Rate of A = 1/10
2Rate of B = 1/6 − 1/10 = 5/30 − 3/30 = 2/30 = 1/15
3B alone = 15 days
Example 3 — Delayed Start

Pipe A fills a tank in 6 hours. Pipe B fills it in 4 hours. A is opened first. After 2 hours, B is also opened. How long in total to fill the tank?

1Work done by A in 2 h = 2 × 1/6 = 1/3 of the tank
2Remaining work = 1 − 1/3 = 2/3
3Combined rate (A + B) = 1/6 + 1/4 = 5/12 per hour
4Time for remaining 2/3 = (2/3) ÷ (5/12) = (2/3) × (12/5) = 8/5 = 1.6 h
5Total time = 2 + 1.6 = 3 hours 36 minutes
Drain pipe rule: Only subtract the drain rate if the drain is open at the same time as the fill pipe. If the tank is being drained after filling, treat them as separate stages.

Complex Examples

Three sources, partial work, or working backwards from the result.

Example 1 — Three Pipes (Two Fill, One Drains)

Pipe A fills in 3 hours, Pipe B fills in 4 hours, Pipe C drains in 6 hours. All three are open. How long to fill the tank?

1Net rate = 1/3 + 1/4 − 1/6
2Common denominator 12: = 4/12 + 3/12 − 2/12 = 5/12 per hour
3Time = 12/5 = 2 hours 24 minutes
Example 2 — Worker Leaves Mid-Job

A can complete a job in 12 days, B in 15 days. They work together for 4 days, then A leaves. How many more days does B need to finish?

1Combined rate = 1/12 + 1/15 = 5/60 + 4/60 = 9/60 = 3/20 per day
2Work done in 4 days together = 4 × 3/20 = 12/20 = 3/5
3Remaining = 1 − 3/5 = 2/5
4B alone at rate 1/15: time = (2/5) ÷ (1/15) = (2/5) × 15 = 6 more days
Example 3 — Tank with a Leak

A pipe can fill a tank in 20 minutes. Due to a leak, it takes 30 minutes. How long would the leak alone take to empty a full tank?

1Fill rate (no leak) = 1/20  |  Effective rate (with leak) = 1/30
2Leak rate = 1/20 − 1/30 = 3/60 − 2/60 = 1/60 per minute
3Leak alone empties tank in 60 minutes
Key pattern: If working together is faster than either alone (which it always should be for filling), your combined rate is correct. If you get a combined time longer than either individual time, you have made a sign error — likely subtracted instead of added, or vice versa.
Practice Questions

Ready to test yourself? Pick a level — 30 questions each.